Travel along Marinduque's Circumferential Road to check all of its six towns
and these are some of the sights you will see, you see...

Island, sea and sky framed by coconut and banana trees.

Rehabilitation and improvement of the Laylay-Ihatub Section (Boac) was completed in December 2011, just one of DPWH infra projects for 2011.

The Ihatub Section is right beside the beach where you could stop for some picture taking.

Another portion of the Laylay-Ihatub Section completed in July 2011.
Beach in Pingan (Gasan) where you could see the town center in the background.

This is the Gasan-Boac Section of the circumferential road which is substantially completed (Km. 109+157.71 - Km. 112+613.20)

In this heat you might wish to make a side trip to Bulusukan Falls (Buenavista)
to cool off for an  hour or so...


This is the Bangcoro-Dayktin Section (Km. 90+1001 - Km. 93+000) which was completed in December 2011.

View of southern Marinduque. (Mainland and Elefante Island, now known as
Bellaroccca  Island Resort and Spa).

Spectacular view of Malindig Volcano from Bellarocca Island Resort and Spa
(photo courtesy of Bellarocca)

Way to Bellarocca.  Road construction ongoing for the Tigwi-Dampulan (Torrijos) and Lipata (Buenavista) Section  (Km. 87+000 - Km. 93+245), but this section has been substantially completed.

Work in progress here at the Tigwi-Dampulan-Lipata Section (Km. 79+530 - Km. 87+000)

Then off you race to Bellarocca with a speedboat, how about that?

This is the Tigwi-Dampulan-Lipata-Yook Section (Km. 74+154 - Km. 76+024.92) that was completed by DPWH contractors in November 2011.